& commissioned for traffic today 22/10/23 with successful speed trial of 117 kmph and inspection of new track & track safe certification by CRS (Commissioner of Railway Safety) Shri. Manoj Arora and Chief Administrative Officer (construction) Shri Vivek Kumar Gupta.
CR has completed 137.67 km multitracking (doubling/3rd/4th line/new line) in current FY from April'23 to till date 2023
➡️Total Length-279.05 km
➡️Completed doubling- 174.85 km (62.65%)
➡️Total Cost- 4882.53 Crs
➡️Expenditure till date- 3200 Crs (65.53%)
➡️Overall physical progress- 86%
➡️Land Acquisition completed- 97.04 Hectare/115 Hectare (84.38%).
🟢Completed sections-
174.78 km (62.65%)
Pune-Shindawane
Ambale-Adarki
Palsi-Jarandeshwar
Satara-Koregaon
Sangli-Shenoli
🟡Near completion sections-
(Likely in this Fin.Year)-
73.70 km (26.41%)
Palsi-Adarki
Satara-Jarandeshwar
Shenoli-Targaon
Sangli-Miraj
🟠In progress-
30.50 km (10.86%)-
Ambale-Shindawane
Targaon-Koregaon
🟢Completed works-
✅Earthwork-2.85 Crs Cum/3.29 Crs Cum (86%)
✅Blanketing- 17 Lcum/36.5 Lcum (47%)
✅Major bridges- 57/75 (76%)
✅Minor bridges/RUB- 365/484 (75%)
✅ROB- 7/10 (70%)
✅Tunnels- 2.6/3
-Saphale-Adarki 274 mtr tunnel completed
-Adarki-Wathar 169 mtr tunnel completed
-Ambale-Shindawane- 110 mtr tunnel in progress
✅Tunnel lengths completed- 475/553 mtr (86%)
✅Station buildings- 29/32
✅Track linking- 200 km/280 km
✅Signalling Electronic interlocking- 22/32 stations
✅OHE Electrification- 151/280 km
Completion of this doubling will improve mobility of trains on Pune-Miraj busy route & will reduce congestion.