#Admin #Moderator Source Cr X Handle
#CRInfraUpdates🟩 Pune - Miraj - Doubling
↔️Length - 279.05 Km.
↔️Length commissioned - 184.88 km.
↔️Remaining - 94.17 km
↔️Overall Physical Progress - 84%
💰 Cost - ₹ 4872.53 Cr
💰 Expenditure till date - ₹ 3320.62 Cr.
🟩Completed doubling - 184.88 km (66.25%)
▶️Pune - Shindawane - 31.67 km
▶️Ambale - Wathar - 78.2 km
▶️Jarandeshwar - Palsi - 8.95 km
▶️Satara - Koregaon - 10.9 km
▶️Shenoli - Sangli - 55.16 km
🟩Near Completion Section- 63.55 km (22.77%)
▶️Wathar - Palsi - 9.39 km
▶️Jarandeshwar - Satara - 7.57 km
▶️Targaon - Shenoli - 39.41 km
▶️Sangli - Miraj - 7.18 km
🟩In Progress Section - 30.57 km (10.9%)
▶️Shindawane - Ambale - 9.45 km
▶️Koregaon - Targaon - 21.12 km
➡Land acquisition - 97.87 /115.93 Hectare Ha (84.41%)
➡Completed works details -
➡Earthwork - 288.82/329.92 Lcum (88%)
➡Blanketing - 17.48/36.50 Lcum (48%)
➡Important Bridges - 2 out of 2 Completed (100%)
➡Major Bridges - 56/73 (77%)
➡Minor Bridge/LHS/RUB - 377/484 (78%)
➡ROB - 7/10 (60%)
➡Tunneling - 2.6 /3 mtr (66%)
➡ Tunneling - 475/545 mtr (87%)
➡Cut and Cover - 15 mtr in Progress
➡ Electrification - 151/ 280 Track km (54%)
➡Station building - 29 /32 (91%)
➡Track linking - 240.42/280 Track km (86%)
➡New Signalling Electronic interlocking - 22/32 Stations (69%)
➡Signalling Indoor and Outdoor works - 11/32 (34%)
🟩Completion of Pune - Miraj - Doubling will help to increase train mobility and will reduce congestion of section.