Ghazipur News: फरवरी के अंतिम में नई रेल लाइन का होगा ट्रायलThe Chief Project Manager (CPM) of Rail Vikas Nigam Limited (RVNL), Vikas Chandra, inspected the new 7 km long railway line between Sonwal and Ghat, costing around ₹200 crore, on Saturday. He inspected the ongoing development work at the under-construction Ghat station and instructed his subordinates to complete the remaining work...
more... by February. Trial and load testing, as well as non-interlocking (NI), are scheduled for the last week of February. The Commissioner of Railway Safety will inspect the line on March 6th. The first phase of the new line, from Sonwal to the City Station, covering approximately 9.6 km, has already completed all tests including the CRS inspection last year. The new route is expected to be operational after the CRS inspection. The inauguration of the project might be done by the Prime Minister in March, but the exact date is yet to be decided.
Rail Vikas Nigam Limited (RVNL) ke CPM Vikas Chandra ne Saturday ko Sonwal se Ghat tak jaane wali, karieb ₹200 crore ki lagat wali, 7 km lambi nayi rail line ka inspection kiya. Unhone under-construction Ghat station par chal rahe vikas kaam ka jaayza liya aur apne mahathaton ko February tak...
more... baki kaam pura karne ka strict order diya. February ke aakhri hafte mein nayi line ka trial aur load testing, saath hi non-interlocking (NI) bhi honi hai. March 6th ko Rail Suraksha Aayukt inspection karenge. Sonwal se City Station tak, karieb 9.6 km lambi nayi rail line ka pehle phase, pichle saal hi CRS aur dusre testing pura ho chuka hai. CRS inspection ke baad, yeh nayi route train chalane ke liye ready ho jayega. March mein PM taraf se project ka udghatan ho sakta hai, lekin date abhi decide nahi hui hai.