Bengaluru: Green Line extension to Madavara will start operations only by Sept-endThe 3.7-km Green Line extension of the Bengaluru Metro from Nagasandra to Madavara, which includes the Manjunath Nagar, Chikkabidarakallu (Jindal Nagar) and Madavara (BIEC) stations, is facing delays and is now expected to be operational by the end of September. The Rs 298-crore project is experiencing delays due to unfinished system...
more... works like electrical and signaling, which require a month to be completed. Testing and trial runs will then take another 45 days. The Commissioner of Metro Rail Safety will need to provide clearance before the line can be launched. The delay is attributed to parliamentary elections, worker shortages, and numerous earlier issues including protests from local villagers, contract cancellations, and access restrictions. The extension will benefit public visiting the Bangalore International Exhibition Centre and residents of Nelamangala, Makali, and Madanayakanahalli who can connect to the city center by boarding the train at Madavara.
Bengaluru Metro ka 3.7-km Green Line extension, Nagasandra se Madavara tak, jo Manjunath Nagar, Chikkabidarakallu (Jindal Nagar) aur Madavara (BIEC) stations ko include karta hai, mein delay aa raha hai aur ab September ke end tak operational hone ki ummeed hai. Rs 298-crore project mein delays ki wajah hai electrical aur...
more... signaling jaise unfinished system works, jinhe complete hone mein ek mahina lagega. Testing aur trial runs mein fir 45 din lagega. Commissioner of Metro Rail Safety ko launch se pehle clearance dena padega. Delay ki wajah parliamentary elections, workers ki kami aur pehle aaye issues jaise local villagers ka protest, contract cancellation, aur access restrictions hain. Extension se Bangalore International Exhibition Centre jane wale public aur Nelamangala, Makali, aur Madanayakanahalli ke residents ko faida hoga jo Madavara se train board karke city center tak ja sakte hain.