USBRL Project: Connecting Jammu & Kashmir!
ЁЯЪЖKatra-Banihal Section
ЁЯПЧя╕ПOverall progress: 93%
Completed...
more... Works:
тЫ░я╕ПTunnel Mining: 163.07Km of 163.88Km
ЁЯЫдя╕ПTrack Laying: 45.66km of 117.7Km
ЁЯМЙ Major Bridges: 22 of 26
-1315m Chenab Bridge: 100%
-777m Bridge No. 43: 100%
-Anji Khad: 83%
please wait...Translate to HindiЁЯЪЖUSBRL Project: Jammu & Kashmir Ko Jodne ka Project!
ЁЯЪВKatra-Banihal Section
ЁЯПЧя╕ПOverall Progress: 93%
Kiye Gaye Karya:
тЫ░я╕ПTunnel Mining: 163.88Km me se 163.07Km
ЁЯЫдя╕ПTrack Laying: 117.7Km me se 45.66Km
ЁЯМЙ Major Bridges: 26 me se 22
-1315m Chenab Bridge: 100%
-777m Bridge No. 43: 100%
-Anji Khad: 83%