Work under Progress
1. Ticket Window on Second Entry : Structure is ready, done with plaster & putti. Doors & Windows need to be installed. It won't take much time
2. FOB Extension : Foundation work in progress
3. Lift (2 nos.) on Both Platform : Both Structures are about to reach on FOB level.
4....
more... Devlopment of circulating area : Two/Three staff quarters will be dismantled. So to provide them accomodation, a multi story building is under construction. Part of Sulabh Complex will be removed too.
5. Extension of parking lot : Part of Garden in Railway colony is sacrificed in lieu of extension.
6. TSS for 2 X 25KV line : New TSS is under construction at Ramganj Mandi. Foundation work is going on.