#PuneSolapurDoubling
Bhalavani to Wadshinge 80% track laid. Deadline for commissioning this section is Jan 2019.
Major Kurduwadi Junction station remodeling work is remaining.
Gulbarga to Sawalagi almost all major work is completed, expected to commision soon.
Boroti...
more... to Kulali section is also completed waiting for commissioning.