Hosapete - guntakallu double electrification update :
*gtl west -(incl) hagari (excl) electrification work completed successfully.
* Gtl - gtl west electrification work in progress half away mark completed.
*hagari - hadinagundu only erected electrical poles are installed
*handinagundu...
more... - BALLARI JN only OHE pit holes are there .
* work yet to start at BAY JN yard
1.GTL st new buliding
2.GTL st new building Ground floor
3.GTL ST new PF
4. electricial load trump shed
5.GTL north cabin
6.GTL oustside with electrification
7.GTL oustside without electrification only erected poles
8&9 . new sub station btn gtl & gtl west under construction
10. GTL west sb
11. after GTL west u can see fully completed electrification.
12 . bantanahala Sb
13.bantanahala exit
14.bevinahalu SB
15.after bevinahalu
16. karnataka/ a.p states border crossing
17.virapura SB
18. hagari yard with only erected poles, wiring not done
19.after hagari
20.haddinagundu
21. ballari city entrance from GTL side with OHE pit holes
22.SN pet RoB not yet completed
23. last OHE pit hole from gtl side at BAY
24. A horse welcomed us at BAY entrance ..HAHA
THE END