The work for the Platform-5 at Jalgaon Jn. has started 2 months ago..
And dead line for platform construction is said till year end and platform 6 till March.
Platform no 5 & 6 was announced to have smooth glow of rail traffic from ST side towards BSL. The stoppage at outer to be reduced.
Working status is as follows:
*...
more... 50-55 % platform has been leveled with use of sand and stones, a stretch at both ends remaining.
* The cement flooring has been covered on 25% surface done.
* 3 Sheds are been constructed.
* The work of extension of F.O.B is in process, one F.O.B on other side is already present.
* Track are already present, and seen goods train on that many times.
* Laying of pebber block not even started.
By this it looks hard to complete the work in given deadlines.