Inaugural run status:-
Station Name/Schedule Departure/Actual Departure/Delayed By.
1. Agartala/12:30/14:40/2:10 hrs.
2. Ambassa/13:20/15:55/3:35 hrs.
3. Dharmanagar/15:32/17:22/1:50 hrs.
4....
more... Karimganj Jn/17:45/19:30/1:45 hrs.
5. Badarpur Jn/18:35/20:10/1:35 hrs.
6. New Halflong/20:50/23:02/2:12 hrs.
7. Lumding/01:30/04:52/3:22 hrs.
8. Hojai/02:21/05:48/03:27 hrs.
9. Jagi Road/03:17/07:17/4 hrs.
10. Guwahati/05:05/08:50/3:45 hrs.
11. New BONGAIGAON/07:52/12:15/4:23 hrs.
12. New Jalpaiguri/12:30/16:32/4:02 hrs.
13. Baruani Jn/20:05/00:45/4:40 hrs.
14. Patliputra/22:25/03:58/5:33 hrs.
15. Mughal Sarai Jn/02:07/07:35/5:28 hrs.
16. Allahabad Jn/04:25/12:07/07:42 hrs.
17. Kanpur Central/06:50/17:24/10:34 hrs.
18. Anand Vihar Terminal/12:50(arrival)/ActualArrival(02:1)/13:24 hrs.
Good Beginning......................May be the Next Brahmaputra mail type train which always runs far beyond Schedule.
**************INAUGURAL RUN DELAYED BY 13 Hours 24 Minutes********************
GREAT BEGINNING AND HOPE FOR IMPROVEMENT IN FUTURE.