Till CAN all works finished except Elathur substation. Expected commission of CLT-CAN in march.
CAN-MAQ/MAJN wiring almost done. The main problem is regarding th substations. There are 5 substations between SRR-MAQ/MAJN. Only one substation is at CS is completed as of now.