Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  
dark modesite support
 
Fri Oct 4 14:18:34 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Advanced Search
<<prev entry    next entry>>
News Entry# 554706
Jun 04 (15:12) Bengaluru Metro's Pink Line Faces Delays Due to Rocky Terrain
Entry# 6084993   
  Past Edits
This is a new feature showing past edits to this News Post.
Bengaluru: Final two TBMs on Pink Line hit rough terrain

The Bengaluru Metro's Pink Line, a 21.26 km line with 18 stations, is facing delays due to rocky terrain encountered by the Tunnel Boring Machines (TBMs) on the final underground stretch between Kalena Agrahara and Nagawara. The TBMs are progressing at half their usual speed, making it difficult to meet the...
more...
initial tunnelling deadline of August-September 2024. The entire line is now unlikely to open by the March 2025 deadline. Seven of the nine TBMs have completed their work, but the remaining two, Tunga and Bhadra, are facing challenges in the last 940 meters each from KG Halli to Nagawara. The rocky terrain has slowed down the tunnelling process, and the completion date is uncertain, with December 2024 being a possible target if the rocky surface gives way to soil. However, even if tunnelling is completed, the entire line's completion depends on various other factors, including station work and other infrastructure.

Bengaluru Metro ke Pink Line, jo ki 21.26 km lamba hai aur 18 stations hai, mein delay aa raha hai kyunki Kalena Agrahara se Nagawara tak ke final underground stretch mein Tunnel Boring Machines (TBMs) ko rocky terrain ka samna karna pad raha hai. TBMs apni usual speed ka sirf aadha...
more...
speed se chal rahe hain, jisse August-September 2024 ka tunnelling deadline meet karna mushkil ho gaya hai. Ab March 2025 ka deadline bhi achieve karna mushkil lag raha hai. Nine TBMs mein se seven apna kaam pura kar chuke hain, lekin baaki do, Tunga aur Bhadra, KG Halli se Nagawara tak ke last 940 metres mein problem face kar rahe hain. Rocky terrain ki wajah se tunnelling process slow ho gaya hai, aur completion date uncertain hai, December 2024 possible target hai agar rocky surface soil mein convert ho jaata hai. Lekin, agar tunnelling bhi pura ho jaata hai, to complete line ka completion depend karta hai station work aur other infrastructure pe bhi.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy