Bhopal News: रेलवे के हिस्से का काम शुरू नहीं होने से बैरागढ़ में आरओबी बनने में देरी, फाटक बंद होने से परेशानीThe construction of an overbridge (ROB) near the railway gate in Sant Hirdaram Nagar (Bairagarh) is progressing slowly. The railway administration has yet to complete its part of the work, which involves laying girders, causing delays. This has resulted in continued inconvenience for citizens due to the frequent closure of the...
more... gate. The construction was announced in 1987 by the then Railway Minister Madhavrao Scindia, but progress was stalled due to various reasons, including objections from the railway, indifference from the state government, and lack of permission from the military administration. The Public Works Department's Bridge Branch commenced work before the previous assembly elections. While the department is actively progressing with its part of the construction, the railway's portion is lagging. The bridge will extend from the 3M E Center side to the railway station, providing convenience to residents of CTO and nearby colonies. The estimated cost of the ROB is approximately 27 crores. The President of the Rail Suvidha Sangharsh Samiti, Parsuram Asnani, has urged the railway administration to expedite their portion of the work to alleviate the inconvenience caused by the frequent gate closures.
Santu Hirdaaram Nagar (Bairagarh) mein railway gate ke paas ROB banne ka kaam bahut slow chal raha hai. Railway administration abhi tak apne hisse mein girder bhichane ka kaam nahin kar paya hai, is wajah se kaam mein der ho rahi hai. Gate bar-bar band hone se citizens ko pahle...
more... jaise pareshani ho rahi hai. Ye ROB ka announcement 1987 mein Madhavrao Scindia ne kiya tha, lekin kaam start nahin ho paya, railway ki objection, state government ki udasinata, aur military administration ki permission na milne jaise karno ke wajah se. Pichle vidhansabha election se pehle, PWD ki Setu Shakha ne ROB ka kaam start kiya tha. Department apna kaam full speed se kar raha hai, lekin railway wala hissa lag raha hai. Bridge 3M E Center side se railway station tak jaayega, jisse CTO aur paas ki colonies ke logon ko suvidha hogi. ROB banne mein 27 crore rupees lagne ka estimate hai. Rail Suvidha Sangharsh Samiti ke president Parsuram Asnani ne railway administration se apna kaam jaldi khatam karne ki appeal ki hai, taaki gate bar-bar band hone ki pareshani se mutli ja sake.