Nana TBM of the Kanpur Metro Records Breakthrough at ChunniganjThe Kanpur Metro Line-1, spanning 23.785 km from IIT Kanpur to Naubasta, is under construction. The 3.619 km KNPCC-05 Package, part of Line-1, has four stations: Chunniganj, Naveen Market, Bada Chauraha, and Nayaganj. TBM S93, nicknamed "Nana," has completed its fourth drive, tunnelling a segment of the up-line tunnel within 70...
more... days. The TBM was used for the construction of the KNPCC-05 package, awarded to Gulermak – Sam India in March 2021 with a 36-month deadline. The "Nana" will be dismantled and stored, awaiting redeployment in early 2025 for tunnelling operations on the Kanpur Metro Line-2's underground Package KNPCC-11, awarded to Kalpataru Projects International Ltd. – Gulermak JV in December 2023.
Kanpur Metro Line-1, jo ki IIT Kanpur se Naubasta tak 23.785 km lamba hai, bana raha hai. Is Line-1 ka ek hissa, 3.619 km lamba KNPCC-05 Package, mein chaar stations hain: Chunniganj, Naveen Market, Bada Chauraha, aur Nayaganj. TBM S93, jisko "Nana" bulaya jata hai, ne apna chautha drive complete kar...
more... liya hai, aur 70 dinon mein up-line tunnel ka ek hissa khudai kar liya hai. Yeh TBM KNPCC-05 package ke construction mein use kiya gaya tha, jiska contract March 2021 mein Gulermak – Sam India ko diya gaya tha, jiska deadline 36 months tha. "Nana" ko dismantle karke store kiya jaayega, aur usko early 2025 mein Kanpur Metro Line-2 ke underground Package KNPCC-11 ke tunnelling operations mein phir se use kiya jaayega. Yeh project December 2023 mein Kalpataru Projects International Ltd. – Gulermak JV ko diya gaya tha.