SBC SMET Electrication Update
ASK nothing So Far but saw some workers Marking Locations/Points at PF2
DRU Fully Electrified
RRB DRU and Little Beyond the Section is Fully Electrified
...
more...
RRB SMET Section is bit Strange Poles and Pits were Spotted in Patches here and There
Sivapur - loop line / main line and the Station electrification is almost complete with wiring Left
TKE - poles Erected
BDVT - Poles Pits Were Seen
SMET - Nothing So Far