SCR Achieves Record Infrastructure Addition of 344 Kms.
The infrastructure addition of South Central Railway has scaled new heights in the current financial year 2021-22 with the record addition of 344 track Kms to the Zone’s rail network. The Construction and completion of 83 Kms of new lines, 197 Kms of Double lines and 64 Kms of Third lines, combined total to 344 Track Kms addition to the rail network during 2021-22 is the highest ever in any financial year, since inception of the Zone.
...
more...
Going into the details, the sections completed as part of 83 Kms New Lines during the current financial year include – 40.2 Kms between Bhadrachalam – Bhavanapalem in the critical coal loading area, 12.2 Kms between Gajwel – Kodakandla, 17.3 Kms between Akanapet –Medak and 13.3 Kms between Magnur – Makthal.
The sections completed as part of 197 Kms of Double Lines include – 29.7 Kms between Umdanagar – Shadnagar, 25.7 Kms between Gollapalli – Mahabubnagar, 17 Kms between Vijayawada – Uppaluru, 48.2 Kms between Narsapur – Bhimavaram – Aravalli, 23.9 Kms between Gundlakamma – Donakonda, 22.5 Kms between Edduladoddi – Maddikera, 26.4 Kms between Kalluru – Gooty, 2.1 Kms Bypass line at Motumari and 1.5 Kms Vijayawada Bulb line.
The sections completed as part of 64 Kms of Third Line during the current fiscal include – 7.8 Kms between Kolnur – Potkapalli, 19.2 Kms between Wirur- Manikgarh, 37 Kms between Kavali – Thalamanchi.